| Project Summary |
Plan |
Actual |
+ Over / - Under |
| Claudia Taylor Ladybird Johnson High School |
| Start Date |
Feb 2006 |
Apr 2006 |
+ 2 |
Completion Date
|
Aug 2008 |
Aug 2008 |
0 |
| Total Project Cost |
$ 71,210,000 |
$ 89,186,262 |
+ $ 17,976,262 |
| Building Only Cost (Constr. Contracts) |
|
$ 73,041,619 |
|
| Site & Design Development (120 acres) |
|
$ 6,777,145 |
|
| Cost per Sq. Ft. |
|
$ 173.91 |
|
Facility Gross Total Sq. Footage
|
395,000 sf. |
420,000 sf. |
+ 44,360 sf. |
| Technology |
|
$ 2,894,319 |
|
| Facility Furniture, Fixtures & Equip. |
|
$ 3,600,000 |
|
| ROCIP |
|
$ 869,811 |
|
| Construction Management Services |
|
$ 2,003,368 |
|
| Progress Bar - Current Phase of Construction |
 |
| Project Team |
 |
Architect: Garza Bomberger & Associates |
 |
General Contractor (GC): Gilbane Building Company |
 |
General Contractor (GC): Joeris General Contractors |
| Walter Scott, Jr., RA |
District Architect & Project Manager, NEISD, Construction Management |
| CM&E Staff |
Project Coordinators, NEISD, Construction Management |
| CM&E Staff |
MEP Inspectors, NEISD, Construction Management |
| Progress Photos |
Lady Bird Johnson HS - Progress Photos |
| Progress Photos |
Lady Bird Johnson HS - Groundbreaking Dedication Ceremony Photos |
| Lady Bird HS Campus: |
Bulverde Rd between Evans & Marshall Roads , San Antonio, TX |
| |
| <Previous |
Page 1 of 2 |
Next> |
This page was last updated on August 23, 2006.
Please contact Theresa Gray,
Web Master,
Construction Management and Engineering
at 804-7270, ext. 372,
regarding webpage-related issues. |
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|