information for the community

North East ISD - Facility Rentals


[ District Policy ] [ Insurance Notice ] [ Rules for using a Facility ] [ Facility Request Form / Information ] [ Inclement Weather Notice ] [ Facility Closure Information ]

Welcome to the North East Independent School District facility use webpage.  NEISD is committed to making campus facilities available for use by the community. First priority is always given to the education of students. The Office of Procurement & eCommerce administers facility use during non-school hours including weekends and evenings. Facility requests are processed on a first-come first served basis. Interested patrons should contact the Office of Procurement & eCommerce to arrange for space in all NEISD campuses. Usage fees vary according to the type of group and the space utilized. Space that may be available includes gyms, auditoriums, classrooms, multi-purpose rooms and playing fields.

For additional information, contact Cindy Salazar at (210) 407-0396 / email at csalaz4@neisd.net or Susanne Baker at (210) 407-0398 / email sbaker@neisd.net.

Use of Facility District Policy

The Board permits and encourages public use of designated school facilities for educational, recreational, civic, or social activities, when these activities do not conflict with school use or with this policy.

Requests for nonschool use of District facilities shall be considered on a first-come, first-served basis; however, sport-related requests shall be considered on a percentage basis of availability schedule due to the limited resources available for use by sports organizations.

Academic and extracurricular campus activities shall always have priority when any use is scheduled. The campus principal or designee has the authority to cancel a scheduled nonschool use if an unexpected conflict arises with a District activity.

Please also refer to North East ISD Policy links below- GKD Use of School Facilities - for any additional information needed.

GKD Local

GKD Legal

Important Insurance Note

NOTE: All groups must submit proof of liability insurance at the same time the Facility Use Application Form is submitted. Liability insurance may be obtained as a separate policy or as a rider. North East Independent School District must be listed as an "Additionally Insured" on the insurance certificate.

RULES FOR USING AN NEISD FACILITIES

Organization MUST provide a Certificate of Insurance Liability naming North East ISD as an additional insured in the amount of one million dollars once vent has been approved.
Any and all school activities take precedence over any facility usage contract.
Coaches MUST bring their contracts with them to all practices.
Absolutely, NO CONCESSIONS are allowed.
NO FOOD or DRINKS (except for water) allowed in the gym.
Absolutely, NO MAIN FIELDS shall be used; only Practice Fields shall be utilized.
NO animals allowed on campus, other than guide dogs assisting the visually impaired individual.
NO access to any other parts of the building.
All TRASH must be picked up.
Teams MUST put equipment back where it was originally located (portable standards only).
Teams/Organizations CANNOT start until the designated time and MUST leave at the designated time.
DO NOT enter the gym office.
For Field use NO RESTROOM facilities will be available.
ADHERE TO CUSTODIAN’S REQUEST.
If these requests are not adhered to the organization will lose its privileges.

Facilities Usage Request Forms and Information

The Facility Usage Request Form allows users to fill out the form within your browser window, then print it out and submit it to the Office of Procurement & eCommerce via mail correspondence, email, facsimile correspondence, or in person. This form is in Adobe Acrobat PDF format. In order to view or print such documents, you must have the free Adobe Acrobat Reader loaded on your computer.

Submit facility requests by

  • eMAIL: Cindy Salazar / csalaz4@neisd.net or Susanne Baker / sbaker@neisd.net
  • FACSIMILE: (210) 804-7134
  • MAIL: Department of Procurement & eCommerce; Facility Rentals, 8961 Tesoro Drive, Suite 317 San Antonio, Texas 78217
  • IN PERSON: at 8961 Tesoro Drive, Suite 317

Resource Links

inclement weather Notice

In cases of inclement weather, updates will be posted as soon as possible. Cancellation of field/gym facilities will be made based on the decision of the Executive Director of the Athletics Department.

Gymnasium Closures

All dates are approximate and subject to change.

During the winter, spring, and summer season, the District's Maintenance Departments schedules gym closures to varnish the gymnasium floors.

As those facilities become available from the District's Maintenance Department, that information will be published here.

Construction Closure Schedule

All dates are approximate and subject to change.

Elementary School Facilities
Facility Start Completion
Bulverde Creek ES Gym HVAC 23-Feb-09 Completed
Camelot ES Gym Replacement* 2-Apr-09 16-Apr-10 **
Castle Hills ES Gym HVAC 9-Mar-09 Completed
Clear Spring ES Gym Replacement* 26-Feb-09 Completed
Coker ES Gym HVAC 19-Jan-09 Completed
Colonial Hills ES Gym Replacement* 26-Mar-09 Completed
Dellview ES Gym Replacement** 26-May-09 29-Mar-10 **
E. Terrell Hills ES Classroom Addition 30-Mar-09 17-Aug-10 **
El Dorado ES Classroom Addition 22-Aug-08 30-Apr-10 **
Encino Park ES 15-Mar-10 15-Apr-10 **
Fox Run ES Gym HVAC 15-May-10 15-Jun-10 **
Hardy Oak ES Gym HVAC 15-Mar-10 15-Apr-10 **
Harmony Hills ES Replacement* 15-Jun-09 Completed
Hidden Forest ES Gym HVAC 22-Jun-09 Completed
Huebner ES Gym HVAC 7-Jun-10 15-Jul-10
Jackson-Keller ES Classroom Addition 1-May-09 15-Nov-10 **
Larkspur ES Classroom Addition 30-Mar-09 5-Aug-10 **
Longs Creek ES Gym HVAC 15-Apr-10 15-Jun-10 **
Montgomery ES Gym HVAC 7-Jun-10 6-Aug-10 **
Northern Hills ES Gym HVAC 15-May-10 15-Jun-10 **
Northwood ES Gym Replacement* 8-Sep-09 12-Jul-10 **
Oak Grove ES Gym Replacement* 14-Sep-09 21-Apr-10
Oak Meadow ES Gym HVAC 15-Jun-10 15-Jul-10 **
Olmos ES Gym HVAC 16-Mar-09 Completed
Redland Oaks ES 7-Sep-09 13-Nov-09
Regency Place ES Gym Replacement* 23-Oct-09 7-Jun-10 **
Ridgeview ES Gym Replacement* 29-Oct-09 14-May-10
Roan Forest ES Gym HVAC 7-Jun-10 6-Aug-10 **
Royal Ridge ES Gym HVAC 13-Jul-09 Completed
Serna ES Gym Replacement* 23-Apr-09 Completed
Stahl ES Gym HVAC 8-Feb-10 22-Mar-10 **
Steubing Ranch Gym HVAC 4-May-09 Completed
Stone Oak Gym HVAC 7-Jun-10 6-Aug-10 **
Thousand Oaks ES 8-Feb-10 15-Mar-10 **
Walzem ES Gym Replacement* 4-May-09 Completed
West Avenue Gym Replacement* 28-Jan-10 Completed
Wetmore ES Gym HVAC 15-Apr-10 15-May-10 **
Wilshire ES Gym Replacement* 9-Dec-09 7-Jul-10
Windcrest ES Gym Replacement* 19-Oct-09 3-May-10 **
Woodstone ES Gym HVAC 7-Jun-10 6-Aug-10 **
Middle School Facilities
Bradley MS Gym HVAC/Addition Pkg VIII 23-Apr-10 31-Jul-11
Bradley MS Competion Gym 7-Jun-10 20-Aug-10
Bradley MS Demo/Rebuild Practice Gym 23-Apr-10 31-Jul-11
Bush MS Gym HVAC 1-Apr-09 Completed
Bush MS Competition Gym 1-May-09 Completed
Bush MS Practice Gym 1-Jul-09 Completed
Driscoll MS Classrooms (Projector Installations) 1-Jun-09 Completed
Driscoll MS  Gym HVAC 5-Oct-09 1-May-10
Driscoll MS Competition Gym Pkg. V 4-Jan-10 1-Mar-10
Driscoll MS Practice Gym 2-Nov-09 4-Jan-10
Eisenhower MS Auditorium 1-Jun-09 Completed
Eisenhower MS Gym HVAC Pkg. V 5-Oct-09 1-May-10
Eisenhower MS Competition Gym 2-Mar-10 1-May-10
Eisenhower MS Practice Gym 4-Jan-10 2-Mar-10
Garner MS Auditorium 1-Jun-09 Completed
Garner MS Classroom Addn/New Gym 2-Feb-09 22-Apr-10 **
Jackson MS Gym HVAC Pkg. V 4-Jan-10 1-May-10
Jackson MS Compeition Gym 2-Mar-10 1-May-10
Jackson MS Practice Gym 4-Jan-10 2-Mar-10
Krueger MS Gym HVAC 1-Apr-09 Completed
Krueger MS Competiion Gym 1-Jun-09 Completed
Krueger MS Practice Gym 1-Jul-09 Completed
Nimitz MS Gym HVAC Pkg VI 23-Apr-10 30-Nov-10 **
Nimitz MS Competition Gym 7-Jun-1- 20-Aug-10 **
Nimitz MS Practice Gym 7-Jun-1- 20-Aug-10 **
Tejeda MS Gym HVAC 1-Apr-09 Completed
Tejeda MS Competition Gym 1-May-09 Completed
Tejeda MS Practice Gym 1-Jul-09 Completed
White MS Gym HVAC Pkg VI 23-Apr-10 31-Dec-10 **
White MS  Competion Gym 7-Jun-10 20-Aug-10 **
White MS  Practice Gym 7-Jun-10 20-Aug-10 **
White MS Fine Arts Addition 1-May-09 Completed
Wood MS Gym HVAC/Addition Pkg VIII 23-Apr-10 31-Jul-11 **
Wood MS Competion Gym 7-Jun-10 20-Aug-10 **
Wood MS Demo/Rebuild Practice Gym 23-Apr-10 31-Jul-11 **
High School Facilities
Center School Gym HVAC 9-Mar-09 Completed
Churchill HS Athletic Addition 15-Aug-08 19-Apr-10 **
Lee HS Gym Renovation 11-May-09 Completed
MacArthur HS Gym HVAC 3-Nov-08 Completed
Madison HS Athletic Addition* 1-May-09 23-Apr-11
N.E. Alternative Gym HVAC 23-Apr-10 31-Oct-10 **
N.E. Alternative Competition Gym 7-Jun-10 20-Aug-10 **
N.E. Alternative Practice Gym 7-Jun-10 20-Aug-10 **
Reagan HS Gym HVAC 3-Nov-08 Completed
Roosevelt HS New Admin, Library, Courtyard 10-Mar-08 Completed
*No disruption of current gym
**Dates changed
All dates are approximate and subject to change.

 

Any questions or comments should be directed to the Web Page Coordinator.

UPDATED: August 19, 2010